May 2020 Update

 

 

It’s been a busy week of work on the Wishaven cabins so far this week:

 

                Accessible parking place and walkway from biffy to cabin 1 was poured and finished

                All windows have been installed and cabins have vapor barrier applied

                Interior wiring is in process

 